When I apply an enterprise task outline code filter in the Task Usage view of
a master project, is there a way to display the work details for the filtered
tasks only? I copied the filtered master project below. What I'm trying to
do is get an idea of how many hours of manufacturing per day we've got going
on, but I can't get the detail view to show ONLY manufacturing, not the two
rows (one summary for the entire sub-project hours, the second the
manufacturing hours). It doesn't add the first row into the comlumn total
when I print, so I'm ultimately getting the information I need, but it's
cluttered and confusing to anyone else who looks at it. Also, if anyone has
a better way of getting a breakdown by enterprise task outline code by day
for all projects, please let me know. I feel like there has to be a less
cumbersome way to do this, something that your average user can do quickly
and easily on their own. Thanks.
Comerica.Published 581.67 hrs 86.85 d? Mon 12/20/04 Wed 4/20/05
Manufacturing 192 hrs 12 d Fri 3/4/05 MANF Mon 3/21/05
Comerica EC Branch.Published 1,508 hrs 92 d? Mon 12/20/04 Wed 4/27/05
Manufacturing 1,103 hrs 27 d Mon 3/14/05 MANF Tue 4/19/05
PriceWaterhouseCooper.Published 9,224 hrs 225 d? Mon 12/20/04 Mon 10/31/05
Manufacturing 4,637 hrs 41 d? Mon 3/28/05 MANF Mon 5/23/05
Manufacturing (18 + 22) 1,384 hrs 22d Wed 9/28/05 MANF Thu
10/27/05 TWP.Published 547.13 hrs 65 d? Tue 12/21/04 Tue 3/22/05
Manufacturing 386 hrs 13 d Mon 2/14/05 MANF Wed 3/2/05
a master project, is there a way to display the work details for the filtered
tasks only? I copied the filtered master project below. What I'm trying to
do is get an idea of how many hours of manufacturing per day we've got going
on, but I can't get the detail view to show ONLY manufacturing, not the two
rows (one summary for the entire sub-project hours, the second the
manufacturing hours). It doesn't add the first row into the comlumn total
when I print, so I'm ultimately getting the information I need, but it's
cluttered and confusing to anyone else who looks at it. Also, if anyone has
a better way of getting a breakdown by enterprise task outline code by day
for all projects, please let me know. I feel like there has to be a less
cumbersome way to do this, something that your average user can do quickly
and easily on their own. Thanks.
Comerica.Published 581.67 hrs 86.85 d? Mon 12/20/04 Wed 4/20/05
Manufacturing 192 hrs 12 d Fri 3/4/05 MANF Mon 3/21/05
Comerica EC Branch.Published 1,508 hrs 92 d? Mon 12/20/04 Wed 4/27/05
Manufacturing 1,103 hrs 27 d Mon 3/14/05 MANF Tue 4/19/05
PriceWaterhouseCooper.Published 9,224 hrs 225 d? Mon 12/20/04 Mon 10/31/05
Manufacturing 4,637 hrs 41 d? Mon 3/28/05 MANF Mon 5/23/05
Manufacturing (18 + 22) 1,384 hrs 22d Wed 9/28/05 MANF Thu
10/27/05 TWP.Published 547.13 hrs 65 d? Tue 12/21/04 Tue 3/22/05
Manufacturing 386 hrs 13 d Mon 2/14/05 MANF Wed 3/2/05