K
Kay
Hi all
I have one question for the task usage view.
I used Text1 to have the project codes.
I used Custom Group by to get the
resource names and project codes to see the utilisation
of my resources.
It displays the resource and below
the project codes
Two questions:
1. When I display % it does not show it. It shows work, but % alloc.
in
the details view is empty
And even worse:
When I assign two resources to a task it displays them as the other
individual resources.
So I get
Res A
Project Code qqq
Res B
Project Code www
Project Code qqq
Res A; Res B
Project Code qqq
But I want to have the resources individually.
Thanks
Kay
I have one question for the task usage view.
I used Text1 to have the project codes.
I used Custom Group by to get the
resource names and project codes to see the utilisation
of my resources.
It displays the resource and below
the project codes
Two questions:
1. When I display % it does not show it. It shows work, but % alloc.
in
the details view is empty
And even worse:
When I assign two resources to a task it displays them as the other
individual resources.
So I get
Res A
Project Code qqq
Res B
Project Code www
Project Code qqq
Res A; Res B
Project Code qqq
But I want to have the resources individually.
Thanks
Kay