Task Usage / Resource Usage Zero Hours

S

screechez

Hello,

I am trying to use Task Usage and Resource Usage views to schedule
individual resource assignments during the duration of the task. A task can
have a total duration for many weeks, but resources (people) are typically
used on-and-off during that task. To schedule this, I use task usage to
assign specific hours to people on specific days of the task duration.

The problem is that the work hours between each resource "shift", the task
usage and resource usage view adds 0h (zero hours). I would prefer to see a
blank entry rather than the 0h as it would make it easy to see when resources
are not assigned to do anything. Right now, the work details on my resource
usage is filled up with a lot of 0h's. Is there anyway to get rid of the
zero hours and have them displayed as blanks? A blank hours would be easier
to see when people are "free" (not doing any work on any task).

Thank you for your help,
 
S

screechez

Apologies for the triple posts on the same subject. Microsoft webpage kept
responding with an error that information could not be received, and I can't
figure out how to delete posts on this discussion group.
 
J

JulieS

No trouble. It's been going on for several days and you're not the
only one whose received the same message. The regular responders to
most all of the newsgroups know of the trouble -- sadly we don't
have the ability to fix it.

Julie
 