Can someone explain why on the Task Usage screen, if I have 'work' hours for
a specific day, and the resource did not perform that work for that day, if I
put zero hour for the actual sometimes the work shifts to the next working
day, and sometimes MS Project will not take the zero actual hours and not
shift the work to the next day. I can't seem to figure the pattern and why
this happens sometime.