I'm trying to create a task usage view that would allow me to filter on
specific resources so that they can easily see what they have upcoming over
the next few weeks. I was able to create a filter that shows the tasks
assigned to the selected resource(s) along with the assignment info for the
resource(s).
What I cannot figure out is how to also have that filtered view show the
other resources that may also be assigned to the task. For example, I want
to filter for tasks where John Doe is assigned which might include tasks
where John is not the only resource assigned to the task. What I would like
to do is show all the tasks to which John is assigned, but show all of the
resources assigned to each of those tasks.
Does anyone know of a way to create this type of a filter/view?
specific resources so that they can easily see what they have upcoming over
the next few weeks. I was able to create a filter that shows the tasks
assigned to the selected resource(s) along with the assignment info for the
resource(s).
What I cannot figure out is how to also have that filtered view show the
other resources that may also be assigned to the task. For example, I want
to filter for tasks where John Doe is assigned which might include tasks
where John is not the only resource assigned to the task. What I would like
to do is show all the tasks to which John is assigned, but show all of the
resources assigned to each of those tasks.
Does anyone know of a way to create this type of a filter/view?