Task vs Assignment

H

Hacknwhack

I have been browsing the Object Browser and am a little confused on what the
difference is between assignments and tasks.

Thanks,
-hack
 
J

John

Hacknwhack said:
I have been browsing the Object Browser and am a little confused on what the
difference is between assignments and tasks.

Thanks,
-hack

hack,
There are basically three parts to the main Project structure. Tasks,
the discrete breakdown of effort to be accomplished to complete an
overall project plan, Resources, the labor or non-labor (e.g. material)
needed to expend effort to complete the tasks, and Assignments, the
bridge between the two.

To keep it simple, look at it this way. When in a Task type of view,
(e.g. Gantt Chart), assignments are the resources assigned to the task.
When in a Resource type of view, (e.g. Resource Usage), assignments are
the tasks the resource is assigned to complete.

Hope this helps.
John