F
FaisalM
Environment:
Project Server 2003 SP1 with Project Professional 2003.
Scenario:
Say I've a task in my project with one resource assigned to it at 100%
starting from this week till the mid of 2006. I want that resource to work on
that task daily say for 4 or 5 hours.
Task Type set to Fixed Unit without effort driven.
Fun Part:
a. If I go to Enterprise Resource Usage view I can see that project
allocated 0.6d or 4.8h of work each day till the finish date of the task. So
far so good.
See the task details on project plan:
http://tinypic.com/fjkwwj.jpg
See the work row in this Enterprise Resource Usage view:
http://tinypic.com/fjkwfs.jpg
See the work for the task in PWA
http://tinypic.com/fjkxe9.jpg
b. The resource entered their time for that task for some day. The resource
worked more than the planned work.
http://tinypic.com/fjkxuq.jpg
(Sometimes the actual work on the task could be more than the planned. But I
want remainder of the planned work for each day to stay the same.)
c. Resource updates his time in PWA. The PM accepts the update in the plan.
Enterprise Resource Usage View shows the time entered for that task as 1d
(or 8h) for that period.
http://tinypic.com/fjkzms.jpg
I go to future days & see that project zeros out the work for some of the
future days & alters work for some & keep it the same for some.
http://tinypic.com/fjl1cn.jpg
http://tinypic.com/fjl1ee.jpg
Same thing is reflected in PWA view of that resource if we scroll through
weekly periods.
http://tinypic.com/fjl3c8.jpg
That makes resource feel that PM/RM haven't assigned any work for this week
so may be I shouldn't work on it!!!!!!!!!
MY QUESTION:
Is there a way that we can fix the work on day by day basis for such a task
where resource has to work everyday no matter if they worked on that task
more for few days?
--
FaisalM
http://www.FaisalMasood.com/
My Project Blog
http://www.faisalmasood.com/blog/msproject
Project Server 2003 SP1 with Project Professional 2003.
Scenario:
Say I've a task in my project with one resource assigned to it at 100%
starting from this week till the mid of 2006. I want that resource to work on
that task daily say for 4 or 5 hours.
Task Type set to Fixed Unit without effort driven.
Fun Part:
a. If I go to Enterprise Resource Usage view I can see that project
allocated 0.6d or 4.8h of work each day till the finish date of the task. So
far so good.
See the task details on project plan:
http://tinypic.com/fjkwwj.jpg
See the work row in this Enterprise Resource Usage view:
http://tinypic.com/fjkwfs.jpg
See the work for the task in PWA
http://tinypic.com/fjkxe9.jpg
b. The resource entered their time for that task for some day. The resource
worked more than the planned work.
http://tinypic.com/fjkxuq.jpg
(Sometimes the actual work on the task could be more than the planned. But I
want remainder of the planned work for each day to stay the same.)
c. Resource updates his time in PWA. The PM accepts the update in the plan.
Enterprise Resource Usage View shows the time entered for that task as 1d
(or 8h) for that period.
http://tinypic.com/fjkzms.jpg
I go to future days & see that project zeros out the work for some of the
future days & alters work for some & keep it the same for some.
http://tinypic.com/fjl1cn.jpg
http://tinypic.com/fjl1ee.jpg
Same thing is reflected in PWA view of that resource if we scroll through
weekly periods.
http://tinypic.com/fjl3c8.jpg
That makes resource feel that PM/RM haven't assigned any work for this week
so may be I shouldn't work on it!!!!!!!!!
MY QUESTION:
Is there a way that we can fix the work on day by day basis for such a task
where resource has to work everyday no matter if they worked on that task
more for few days?
--
FaisalM
http://www.FaisalMasood.com/
My Project Blog
http://www.faisalmasood.com/blog/msproject