S
spondee
Is this possible & how would I do it???
What are you attempting to achieve? It's possible that another approach may
give you the result you are looking for.
I'm looking for 'flexibility' in those task schedules! I want to see
WHEN I've worked and how much, rather than a 'due' date.
I am a writer. Self-employed. Only me. No big company, No IT's to
check with! Can't afford 'consultants' or 'classes'.
Have multiple 'projects' ongoing, in various stages of completion..
Most have extremely flexible, self-imposed deadlines. Even the
sub-tasks may be months in the future.
Many of these 'projects' I only work on sporadically (putting out
fires elsewhere). Which is EXACTLY what I'm trying to correct in my
work habits by using PROJECT.
In the past few years, as I've taken on more work, I find I've 'lost
track' of a small paying project while I deal w/a big pro bono
project! Or I fail to set up the steps (research etc), necessary for
the next PAYING job! Or I get the 'small' paying gigs done, but no
work on some major long-term projects.
I've always MET every assigned 'deadline' but hate them so much will
even turn down an assignment because of 'em!
I've never worked w/ fixed time lines before (too much like
'deadlines' to me!). Nor have I had to look at a realistic timeliness
stretching years into the future! And I guess I'm trying to avoid
them.
OTOH, I use and have learned complicated software! Outlook & Office
(I'm up to 2003), Win Xpro, Specialized writing software. MONEY.
Lots of barely functioning share/freeware over the years.
So I CAN learn and use Project2000. Don't know why I'm so hung-up
with it! I just probably need to ask a whole bunch of stupid
questions and run a bunch of 'trials'! (But I do think, compared to
other software titles, the help files suck!).
I think that if I could actually SEE various forms/styles/types of
Project Files that the self-employed or VERY small business have set
up, that it would be very helpful...
It appears to me that you're basically using Project as a time-tracking
system. Although I wouldn't have chosen Project to do this,
want to consider:So here are some suggestions that you might
1. Give the task an end date months (or even years) into the future. To do
this
1a. View | Resource Sheet and create a resource entry (you!)
1b. View | Gantt chart and create a task. Set the Type to "Fixed
Duration", the duration to 400d, the work to 0 and yourself as the resource
assigned to the task.
Now, you can use the View | Resource Usage display to track when you
actually did work on this assignment in the Actual Work cells.
2. Do the opposite: create a milestone task which has a start date the
same as the end date and 0 hours of work and with a task type of Fixed
Units. Assign yourself as the resource and then track your hours in the
View | Resource Usage display by entering your hours in the Actual Work
cells.
Both of these will create a bar in the Gantt display. Don't use that
display. Instead, use the Network Diagram or Calendar display.
1. Give the task an end date months (or even years) into the future. To do
this
1a. View | Resource Sheet and create a resource entry (you!)
1b. View | Gantt chart and create a task. Set the Type to "Fixed
Duration", the duration to 400d, the work to 0 and yourself as the resource
assigned to the task.
Now, you can use the View | Resource Usage display to track when you
actually did work on this assignment in the Actual Work cells.
Want to reply to this thread or ask your own question?
You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.