J
jov
Hi everybody,
I've created a task programmaticaly and set its Work to be 50hrs as well
as explicitly set its Start and Finish dates. I now create actuals
against the task for discreet time periods(5h 1day, 7h another etc.), I
now see that they cause the tasks Work to be equal to the sum of those
actuals and equaly the Start and Finish to reflect those actuals. Is
there anyway to not have it do this... to leave the Work allocation for
the task alone?
thanks,
John
I've created a task programmaticaly and set its Work to be 50hrs as well
as explicitly set its Start and Finish dates. I now create actuals
against the task for discreet time periods(5h 1day, 7h another etc.), I
now see that they cause the tasks Work to be equal to the sum of those
actuals and equaly the Start and Finish to reflect those actuals. Is
there anyway to not have it do this... to leave the Work allocation for
the task alone?
thanks,
John