J
johengs
I have quite a simple problem, which I have been unable to figure out
how to solve using Microsoft Project 2003.
A task has a specific work load, say 100 hours. There are two or more
resources which are assigned this same task. Each resource has defined
the number of units, which the resource uses on the task (for instance
with three resources the numbers could be RA: 50%, RB: 100% and RC:
25%). Now the question is:
How do I get Project to schedule the work between the resources so
that the task will end as quickly as possible?
Assuming 5-hour days, the right solution for the example case
specified above would be about 11,4 work days, so that resource A
works 2,5 hours per day, resource B works 5 hours per day and resource
C works 1,25 hours per day. Somehow I have not been able to command
Project to calulate this for me so that if I for instance change one
of the allocation units (RB: 100% -> 75%, for instance), the optimal
division of work would be re-calculated (so that all resources would
finish/stop working at the same day).
I would appreciate any help on this, because I have done everything to
find the answer to this, but with no results so far. Please ask if
something was unclear about my problem description.
BR,
Johan
how to solve using Microsoft Project 2003.
A task has a specific work load, say 100 hours. There are two or more
resources which are assigned this same task. Each resource has defined
the number of units, which the resource uses on the task (for instance
with three resources the numbers could be RA: 50%, RB: 100% and RC:
25%). Now the question is:
How do I get Project to schedule the work between the resources so
that the task will end as quickly as possible?
Assuming 5-hour days, the right solution for the example case
specified above would be about 11,4 work days, so that resource A
works 2,5 hours per day, resource B works 5 hours per day and resource
C works 1,25 hours per day. Somehow I have not been able to command
Project to calulate this for me so that if I for instance change one
of the allocation units (RB: 100% -> 75%, for instance), the optimal
division of work would be re-calculated (so that all resources would
finish/stop working at the same day).
I would appreciate any help on this, because I have done everything to
find the answer to this, but with no results so far. Please ask if
something was unclear about my problem description.
BR,
Johan