I am facing from a while with a problem related to the task_dur field
in msp_tasks table and it's "equivalent" property duration.
I use a sql stored procedure to write many tasks in the sql server
table and after I read these datas from MSProject, but some tasks
appear to have a null duration ( 0h ) even if the task_dur field is
not zero and the field EXT_EDIT_REF_DATA is set to '1'. The
strangeness is that the duration in the table is well calculated
(duration in minutes * 60) but I cannot see it in Project.
I am getting crazy with this problem!
Gabriele
 
M

Mike Glen

Hi Gabriele ,

Try posting on the server or developer newsgroup. Please see FAQ Item: 24.
Project Newsgroups. FAQs, companion products and other useful Project
information can be seen at this web address: http://www.mvps.org/project/.

Mike Glen
Project MVP
 
J

JackD

Did you open and save the project using MSProject after you have entered the
data and set the proper flags? If not, then the field will not be
calculated.
 