TASK_START_DATE (TIME ZONE)

A

Amit

I have a project server in Mountain Time zone, and I am in Eastern Time zone.
When I use this server to pull the project tasks, I get time differences on
the TASK_START_DATE and TASK_FINISH_DATE by 2 hours. For example if the task
starts at 8 pm in Mountain Time zone, I see 10 PM in Eastern Time zone. I do
not want to see this time difference. Is there any setting on project server
that I can turn off so that task does not have time difference?
 
R

Ray McCoppin

Project Server stores the dates and time using the time zone that the server
is located in. Each client then converts the dates and times to its local
time zone using offsets. If you want to see mountian times just reset you
pc to the mountain time zone.

Hope this helps
 
A

Amit

I won't know where my client server is going to be. Therefore, it is hard to
figure out the offset value. Is there any property on the dataset that can
provide me the offset value?
 