Taskpad views

G

Gerald

We have tried setting taskpad views to "Todays Tasks"
and "Active Tasks for Selected Days" and both views are
showing tasks far in the future, some are recurring, some
are not. Also, setting "Active Tasks for Selected Days,"
we find no place to set the selected days.

Any help here?

Thanx
 
G

Gerald

If the Due Date is set and not the Start Date, the task
will show from the date it is created. Setting the Start
Date controls the point from which the item shows in the
Taskpad.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question