Tasks added from PWA My work/My taska are always Fixed Units type

K

Kalin

Tasks added from PWA My work/My taska are always Fixed Units type.
How can I make them by of Fixed wok type. Tried to change the
dbo.MSP_PROJECTS.PROJ_OPT_DEF_TASK_TYPE fron the Draft project database but
it didn' woked - tasks are added as "Fixed Units"
 
J

Jackson T. Cole

2003 or 2007?

What is the default task type in Project Professional? I'm not sure if
the Enterprise Global has any influence on default task type. I think Project
Pro ships with "Fixed Units" as default, though.

My $.02 worth ...!

JTC
 
K

Kalin

It's 2007.
Project Professional settings has nothing to do with the PWA. Never the less
I have tried setting the default type of tasks to Fixed work there. I did the
same with the Enterprise Global. They both worked with Project Professional.
But when I use PWA to add Tasks from My tasks they are ALWAYS Fixed Units, no
matter what Project Professional settings are, nor changing the default type
of tasks for the project directly editing the SQL database field.
 