Tasks are not updated to reflect changes in the Project....

A

aka_iky

Hi --

I made changes to a project on our Project Server and saved the changes. I
then republished the assignments.

When I go to view the tasks assigned to me, the tasks displayed are the old
tasks assigned to me and not the updated tasks.

Any suggestions how I might be able to resolve this issue would be greatly
appreciated.

Thanks

-- Mike
 
D

Dale Howard [MVP]

Mike --

I am assuming you manually updated tasks with actuals in the Microsoft
Project plan. If this is the case, you need to do the following:

1. Select the tasks in which you entered actuals
2. Click Collaborate - Publish - Republish Assignments
3. Make sure the "Selected tasks" option is selected at the top of the
dialog
4. Select the "Overwrite actual work entered by resources" option
5. Click OK

Doing the above steps will "push" your actuals from the Microsoft Project
plan to each resource's timesheet in PWA for the selected tasks. Hope this
helps.
 
A

aka_iky

Hi Dale --

Thanks for the solution! It worked perfectly and fixed my problem.

-- Mike
 