Hi
Project manager added a new task (only one task) to resource. After
adding the task project manager have done publish -> New and changed
assignments. Actually, this is the step to assign a new task to an
enterprise
resource. But, the resource was not able to view the task in his timesheet
for that
project only (for remaining projects he was able to see and other project
managers has assigned new tasks to him. And those tasks were visible.
But, for one project the resource was not able to see that task. when I
logged into
project web access as an administrator, selected that resource,
(resources -> adjust actuals) i was also not able to see that task in his
timesheet.
Any suggestions on this would be really appreciated.
Thank you,
Shiva Chaitanya.
Project manager added a new task (only one task) to resource. After
adding the task project manager have done publish -> New and changed
assignments. Actually, this is the step to assign a new task to an
enterprise
resource. But, the resource was not able to view the task in his timesheet
for that
project only (for remaining projects he was able to see and other project
managers has assigned new tasks to him. And those tasks were visible.
But, for one project the resource was not able to see that task. when I
logged into
project web access as an administrator, selected that resource,
(resources -> adjust actuals) i was also not able to see that task in his
timesheet.
Any suggestions on this would be really appreciated.