L
Ldyflyr
Hi:
Is it possible in MS Project to have a task calculate it's percent complete
based on a series of other tasks being completed? The "hitch" is that it is
not a summary task.
For example, I have 3 gropus of tasks, A, B an C. They are different parts
of the project plan. I want a section at the end of the plan to show the %
Complete for each of the groups of task and then use a summary task to tell
me how combined total % complete.
So I want my new Task X to be the summary task A, Task Y to be the summary
task B, and Task Z to be the summary task C.
I hope that makes sense.
Thanks
Is it possible in MS Project to have a task calculate it's percent complete
based on a series of other tasks being completed? The "hitch" is that it is
not a summary task.
For example, I have 3 gropus of tasks, A, B an C. They are different parts
of the project plan. I want a section at the end of the plan to show the %
Complete for each of the groups of task and then use a summary task to tell
me how combined total % complete.
So I want my new Task X to be the summary task A, Task Y to be the summary
task B, and Task Z to be the summary task C.
I hope that makes sense.
Thanks