Tasks causing overallocated resources

R

Rich

Does anyone know how I can see what tasks are causing overallocated
resources? I can see in the resource view which resources are
overallocated, but can't seem to find anything that shows me the exact
tasks that are causing the problem. Thanks.
 
J

Jan De Messemaeker

Hi Rich,

The resource usage view will show you which tasks and when
HTH
 
M

Mitch Johnson

Rich,

You might want to try various third party add-ins. Do a google search for an
add-in called Oasys Scheduler. It lets you see which tasks have resource
conflicts right on the gantt view, which seems to be exactly what you're
looking for.
 