I have some tasks assigned to multiple resources on Project Server so that 2
or more people can see them in their task list. When one resource updates
the task as 100% complete, it only updates the task as 50% in the project.
Is there a way to make it so that the task is updated at 100% in the project
when only one resource updates the task as 100% complete?
Thanks,
Andy