R
Rami
Hi
As you know, you can create a relationship between tasks, like
Finish-To-Start.
And as the name suggests, the next task should not start until the previous
finishes. But in Project Server, the resource can start that Successor task
without having the Predecessor task finished.
I am really astonished how Primavera stops you from doing such thing but Ms
Project does not!!
Thanks
As you know, you can create a relationship between tasks, like
Finish-To-Start.
And as the name suggests, the next task should not start until the previous
finishes. But in Project Server, the resource can start that Successor task
without having the Predecessor task finished.
I am really astonished how Primavera stops you from doing such thing but Ms
Project does not!!
Thanks