Tasks do not appear in PWA

A

Arlo

We just finished a migration of Project professional from
2002 to 2003. We have a really odd situation. We add a
task to an imported project and assign one of the
enterprice resources to it and save and publish it.

When the resource opens PWA it says that there are no new
tasks waiting AND the task and project are not visible on
the taskview. But when moving on to the resources view and
filtering on the user, both project and task are visible
as assigned.

This only occurs on imported projects. New projects work
fine.
Deleting and importing again doesnt solve our problem. It
exists before and afer installation of SP1.

We figure somehow project are corrupted during the update
from 2002 =>2003, but are not sure.

Anybody? help would be very appreciated.
 
A

Arlo

It appears that during the conversion of the 2002 projects
to 2003, the standard booking type is set to committed,
but in all the converted projects, the booking type of the
resources is somehow set to proposed.

everytime a project is republished it seems to dissappear
from the PWA.


Changing the booking type back for each project
individually solves the problem
 