Tasks does not move

M

meg99

Using 2003. I have a task in one project attached FS to a task in
another project inside a Master Project

Master Project
Task A (milestone)

SubProjct x
Task xa (milestone)

Thus xa is a predecessor to task A. Problem is, task A does not move
to reflect date of xa

anybody know why?

meg99
 
M

meg99

Using 2003.  I have a task in one project attached FS to a task in
another project inside a Master Project

Master Project
      Task A (milestone)

SubProjct x
      Task xa (milestone)

Thus xa is a predecessor to task A.  Problem is, task A does not move
to reflect date of xa

anybody know why?

meg99

Never mind. Broken link prior to xa.
meg99
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top