D
Dave
Hello Everyone,
Here is the situation. I have certain tasks in my project that have a
duration of .5hrs, these tasks have to been set to have a fixed duration. We
are using Hours of work done per period as our tracking method. As long as
the user enters time grater that or equal to the scheduled time everything
is ok that is if the resource goes and updates his task and enters .5h or
greater it is ok, but the moment he enter say .4hrs the task in my project
plan becomes 8hrs and the resource utilization becomes 5%.
So a user can enter a time as long as it is delayed or on time but cannot
enter time if he is ahead of schedule.
Anyone know why this is happening.
Thanks
Dave
Here is the situation. I have certain tasks in my project that have a
duration of .5hrs, these tasks have to been set to have a fixed duration. We
are using Hours of work done per period as our tracking method. As long as
the user enters time grater that or equal to the scheduled time everything
is ok that is if the resource goes and updates his task and enters .5h or
greater it is ok, but the moment he enter say .4hrs the task in my project
plan becomes 8hrs and the resource utilization becomes 5%.
So a user can enter a time as long as it is delayed or on time but cannot
enter time if he is ahead of schedule.
Anyone know why this is happening.
Thanks
Dave