I am having an issue with MS Project that I have never seen.
The task will not let me change the duration. The task will let me
type a number of days into the duration field but when I hit ok the
task goes back to 0 days. Certain activities keep wanting to be a
milestone.
What is going on here?
I'm figuring it's something that will be able to be fixed in a couple
of minutes.
Thanks,
Lou