C
Clara
I have some resources who cannot seem to successfully import some of their
timesheets into their tasksheets. One timesheet will import successfully,
then the next one won't. They receive a timeout error and are returned to the
Import Timesheet screen. The result it, of course, our project plans do not
update with the time resources have entered on their timesheets.
We are using Project server 2007 but have not applied SP1 yet.
I have looked at dozens of their timesheets and cannot find a common thread
on why this would occur. Anyone else seen this and found a way to correct
it?
timesheets into their tasksheets. One timesheet will import successfully,
then the next one won't. They receive a timeout error and are returned to the
Import Timesheet screen. The result it, of course, our project plans do not
update with the time resources have entered on their timesheets.
We are using Project server 2007 but have not applied SP1 yet.
I have looked at dozens of their timesheets and cannot find a common thread
on why this would occur. Anyone else seen this and found a way to correct
it?