We have a number of generic resources eg:
engineer
senior engineer
CIO
etc.
These resources are NOT tied to a specific windows account (unlike
real people).
However tasks assigned to these resources appear in 'My Tasks' list -
for me personally!
Why?
This happenes whether or not I am the project owner....why?
It's very annoying - these aren't my tasks.
What governs who gets tasks for generic resources?
Al
engineer
senior engineer
CIO
etc.
These resources are NOT tied to a specific windows account (unlike
real people).
However tasks assigned to these resources appear in 'My Tasks' list -
for me personally!
Why?
This happenes whether or not I am the project owner....why?
It's very annoying - these aren't my tasks.
What governs who gets tasks for generic resources?
Al