Tasks from Projects that are Complete Still Showup in Tasks Screen in PWA

C

Charles L. Simpson

On our projects loaded to Project Server that have been marked as complete
by the Project Managers (% Complete = 100% and % Work Complete = 100%) there
are tasks that still show up in the Project Web Access Tasks screen for the
users from these projects.

It's weird because on a particular task, PWA tells me that I have 32h
remaining work when in Project Pro I have 0h remaining work and everything
in the project is 100% complete.

I have republished everything (all, and assignments) and still PWA thinks
that there are tasks that are not complete.

Any help would be appreciated.

Thanks!
---------------------------------------------------------------
Charles L. Simpson
ACT, Inc.
---------------------------------------------------------------
Current Setup:
WSS 2.0 (no service packs)
Project Server 2003 SP1
SQL Server 2000 SP3a
FrontPage 2003 SP2
-----------------------------------------------------------------
 
D

Dale Howard [MVP]

Charles --

After manually updating these tasks in Microsoft Project Professional, are
you completing the following steps:

1. Click Collaborate - Publish - Republish Assignments
2. Select the "Overwrite actual work entered by resources" option
3. Click OK

Let us know.
 
C

Charles L. Simpson

Thanks Dale ... I'll try this and let you all know!

Charles L. Simpson


Dale Howard said:
Charles --

After manually updating these tasks in Microsoft Project Professional, are
you completing the following steps:

1. Click Collaborate - Publish - Republish Assignments
2. Select the "Overwrite actual work entered by resources" option
3. Click OK

Let us know.
 
C

Charles L. Simpson

Thanks Dale ... that worked!

Does anyone know of the consequences of overwriting the actuals reported by
the resources?

Thanks!

Charles L. Simpson


Charles L. Simpson said:
Thanks Dale ... I'll try this and let you all know!

Charles L. Simpson
 
D

Dale Howard [MVP]

Charles --

The actuals in the project overwrite the actuals on each team members's
timesheet in PWA. You have the option to republish assignments for the
entire project, for a selected group of tasks, for an individual task, or
even for one or more individual assignments (in the Resource Usage view).
Hope this helps.
 
C

Charles L. Simpson

That's great Dale ... Thanks!

Dale Howard said:
Charles --

The actuals in the project overwrite the actuals on each team members's
timesheet in PWA. You have the option to republish assignments for the
entire project, for a selected group of tasks, for an individual task, or
even for one or more individual assignments (in the Resource Usage view).
Hope this helps.
 

Ask a Question