Hi,
1. I have three phases (Construction, Code Review, and Unit Testing).
2. The two phases (Code Review and Unit Testing) should run in
parallel with Construction
3. The start date and end date for this trunk is from 1-Aug-2008 to 7-
Aug-2008 respectively
4. There are two resources; R1 would handle development, R2 would
handle code review and testing
5. The efforts are perfect for construction phase
I would like to if I could accomplish this:-
6. Need to add a task Code review and assign the start date from 1-Aug
to 7-Aug and assign this task to R2 without changing the parent effort
duration
7. Need to add another task Unit Testing and assign the start date
from 1-Aug to 7-Aug and assign this task to R2 without changing the
parent effort duration
I am using MS Project 2003.
Kindly help!
Thank you,
Dev
1. I have three phases (Construction, Code Review, and Unit Testing).
2. The two phases (Code Review and Unit Testing) should run in
parallel with Construction
3. The start date and end date for this trunk is from 1-Aug-2008 to 7-
Aug-2008 respectively
4. There are two resources; R1 would handle development, R2 would
handle code review and testing
5. The efforts are perfect for construction phase
I would like to if I could accomplish this:-
6. Need to add a task Code review and assign the start date from 1-Aug
to 7-Aug and assign this task to R2 without changing the parent effort
duration
7. Need to add another task Unit Testing and assign the start date
from 1-Aug to 7-Aug and assign this task to R2 without changing the
parent effort duration
I am using MS Project 2003.
Kindly help!
Thank you,
Dev