Tasks in Project appear as Summary tasks in PWA

C

ceichhammer

Hi,

I've got a problem with Project Web Access. In Project Web Access
appear tasks as summary tasks (like the following example):

Project Plan:

Summary Task a 1
Task b 1.1
Task c 1.2
Summary Task d 2
Task e 2.1
Task f 2.2

Appear in PWA as

Summary Task a 1
Summary Task b 1.1
Summary Task c 1.1.1
Summary Task d 1.1.1.1
Task e 1.1.1.1.1
Task f 1.1.1.1.2

As consequence, my collegue cannot write down the actual work. Can you
help me?

Ciao,
Christine
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.