Tasks in project plan dont appear indent in PWA views

R

Richiee

The problem is that in PWA views when I click in any project the project
plan appear showing all task in one level, not indent.

Any help please!
 
B

Brian K - Project MVP

Richiee said:
The problem is that in PWA views when I click in any project the
project plan appear showing all task in one level, not indent.

Any help please!

click the View Options link just above the view area.

then check the box marked Show summary tasks.
 