S
Surendra
Hi,
I want to show tasks involved in the longest chain with a particular
colour(say brown). I do not know how to identify task involved in the longest
chain (may not be necessarilly the critical path).I am new to VBA and I have
to do this through macro.
Please let me know how to do this.
eg. My project's summary task shows project duration as 101 days whereas sum
of the critical task is coming to 89 days and total task's duration is 234
days. I want to know which are the tasks which contribute to this 101 days.
Thanks in advance.
I want to show tasks involved in the longest chain with a particular
colour(say brown). I do not know how to identify task involved in the longest
chain (may not be necessarilly the critical path).I am new to VBA and I have
to do this through macro.
Please let me know how to do this.
eg. My project's summary task shows project duration as 101 days whereas sum
of the critical task is coming to 89 days and total task's duration is 234
days. I want to know which are the tasks which contribute to this 101 days.
Thanks in advance.