E
Elwood_33
I am trying to build a production schedule using numerous subprojects in a
master project and sharing resources using a resource pool. This is so
"novice" users can access very small projects to update actual progress
without risking inadvertent changes to tasks in the master project.
Before attempting the master project scenario I built the schedule with the
desired task dependencies in a single project, with resources, which seemed
to work as expected.
In the newly created master and sub-projects, however, tasks continue to
unexpectedly move out into the future, despite no load on the applicable
resources earlier in the schedule and even when task dependencies are
removed. I am to the point where I can't bring the scheduled start date for
a task back to where I want it (today) for either of two unlinked tasks in a
sub-project consisting of only those two tasks will all internal and external
links removed.
I've been trying to figure this out all day but have had no success.
Does anyone have any suggestions?
master project and sharing resources using a resource pool. This is so
"novice" users can access very small projects to update actual progress
without risking inadvertent changes to tasks in the master project.
Before attempting the master project scenario I built the schedule with the
desired task dependencies in a single project, with resources, which seemed
to work as expected.
In the newly created master and sub-projects, however, tasks continue to
unexpectedly move out into the future, despite no load on the applicable
resources earlier in the schedule and even when task dependencies are
removed. I am to the point where I can't bring the scheduled start date for
a task back to where I want it (today) for either of two unlinked tasks in a
sub-project consisting of only those two tasks will all internal and external
links removed.
I've been trying to figure this out all day but have had no success.
Does anyone have any suggestions?