Tasks Missing in View Resource Assignment View

M

Minhchau

We've been using Project 2003 since March 2005. We converted all of our
Enterprise projects over Project 2003. Recently, I use the renamer tool to
rename some of these converted projects. When I clicked on View Resource
Assignment under Resources tab to go to one of the view that I created, I
could not find most of the tasks under one of those projects that I renamed.
Some of the tasks for this project still shows up, but a few resources were
missing. The view that I created has these column headings: Project Name,
Task Name, Start, Finish, Resource Name, Work, Actual Work.

We are in the Managed Period system (Timesheets). I did republish the
project after I renamed it. There're no constraints on the view either.

Please advise on what I can do to make this view show all the tasks in all
my projects.