Hi
I've asked the question before, but I'll try again.
I just made a clean install of WSS and ProjectServer.
I've added my self as a resource to the Enterprise Resource Pool, created a
new project, assigned a task to the resource and published the project to
PS.
When I logon to PWA I get the "You have no new tasks assigned to you"
message on the home page.
When I go to "Projects" in PWA, I can see the published project and my name
(as a resource) as the one assigned to this task, but I can't register any
time spent on the task.
When I use Outlook to "Import New Assignments" I don't get any new tasks.
Any hints would be nice.
I think I saw a question in this forum a bit simlar to this, where the
answer was to use the Enterprise Template to build the project, but I can't
seem to find anything in the help files on how to do this.
Regards
Jesper Berg
I've asked the question before, but I'll try again.
I just made a clean install of WSS and ProjectServer.
I've added my self as a resource to the Enterprise Resource Pool, created a
new project, assigned a task to the resource and published the project to
PS.
When I logon to PWA I get the "You have no new tasks assigned to you"
message on the home page.
When I go to "Projects" in PWA, I can see the published project and my name
(as a resource) as the one assigned to this task, but I can't register any
time spent on the task.
When I use Outlook to "Import New Assignments" I don't get any new tasks.
Any hints would be nice.
I think I saw a question in this forum a bit simlar to this, where the
answer was to use the Enterprise Template to build the project, but I can't
seem to find anything in the help files on how to do this.
Regards
Jesper Berg