I have a project that I'm wonderinf if it has a corrupt
or not. If I try to view a report, with NO GROUP
assigned, no tasks display. If I select any of the other
groupings, they display. Another project displayed using
NO GROUP works fine. Since this grouping cannot be
changed or deleted, they should work the same, right?
In addition to that, I have a couple of tasks (ID 6 and 7)
that do not display regardless of the grouping. They do
show up on the web server.
I admit I'm a novice and am finding this product a bit
technical for my liking, maybe some training would be in
order.
or not. If I try to view a report, with NO GROUP
assigned, no tasks display. If I select any of the other
groupings, they display. Another project displayed using
NO GROUP works fine. Since this grouping cannot be
changed or deleted, they should work the same, right?
In addition to that, I have a couple of tasks (ID 6 and 7)
that do not display regardless of the grouping. They do
show up on the web server.
I admit I'm a novice and am finding this product a bit
technical for my liking, maybe some training would be in
order.