tasks not displaying

J

Joan

I have a project that I'm wonderinf if it has a corrupt
or not. If I try to view a report, with NO GROUP
assigned, no tasks display. If I select any of the other
groupings, they display. Another project displayed using
NO GROUP works fine. Since this grouping cannot be
changed or deleted, they should work the same, right?

In addition to that, I have a couple of tasks (ID 6 and 7)
that do not display regardless of the grouping. They do
show up on the web server.

I admit I'm a novice and am finding this product a bit
technical for my liking, maybe some training would be in
order.
 
M

Mike Glen

Hi Joan,

Try posting on the server newsgroup. Please see FAQ Item: 24. Project
Newsgroups. FAQs, companion products and other useful Project information
can be seen at this web address: http://www.mvps.org/project/.

Mike Glen
Project MVP
 
S

Steve House

Training would be a definite help - hopefully with a course that emphasizes
the management skills of project management and less emphasis on the project
software per se. The software is deceptivly easy to use but the details on
the best ways to use it or why you should approach things in a certain way
are often far from obvious.

As for why your tasks aren't appearing, that one I haven't encountered so
I'll have to defer to others.

Steve House
MS Project MVP
 