Using PWA 2007.
I have 2 projects that i have assigned tasks to for my team. However, each
resource can only see tasks from one project. How do I get the tasks to show
up for multiple projects?
 
D

Dale Howard [MVP]

Tony C --

I can think of three possible reasons for this:

1. Did you actually publish the second project?

2. Open the project in which your resources cannot see tasks and click
Tools - Build Team from Enterprise. Is the Booking type value set to
Committed for each team member? If it is set to Proposed, your team members
cannot see their tasks until you set the value to Committed.

3. Is the project Start date more than two weeks in the future? This would
mean your team members cannot see tasks in this project if they have the
Current Tasks option selected on the My Tasks page.

Let us know if this helps.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top