Project Server 2007: I want to be able to assign individual Resources for
some Project Tasks at a different Units% to the value associated with the
resource in the Enterprise Resource Pool. Changing the Units% allows selected
staff to share some tasks without affecting the task duration or to work on
several tasks in parallel.
Unfortunately I have found that these Task assignments do not show up in the
Task Views for the users. They do show up correctly in the Project Centre
view of the plan and in the Resource Availability view for the Resource.
What do I need to do?
some Project Tasks at a different Units% to the value associated with the
resource in the Enterprise Resource Pool. Changing the Units% allows selected
staff to share some tasks without affecting the task duration or to work on
several tasks in parallel.
Unfortunately I have found that these Task assignments do not show up in the
Task Views for the users. They do show up correctly in the Project Centre
view of the plan and in the Resource Availability view for the Resource.
What do I need to do?