hi,
same problem here..however i checked the assignment owner and it is blank..same for the timesheet..
what seems to be stranged happening is that the publisher of the plan is the who is seeing the tasks if the publisher goes to My Tasks page although the Resource Name columns still displays the original assignments..
hope you can reply soon..thanks!
Ben Howard wrote:
RE: Tasks not showing up on my tasks
15-Sep-09
Check the assignment owner for the user. This is done is PWA within Edit the
user. It should not be blank, it should be set to the user
Also, presumably the project is published
Can you see the work via the resource centre
Let us know
--
Thanks, Ben