Does any one knows in what order does MSP2007 sets the tasks ?
1. I do not have summary tasks
2. It seems start dates are not the critiria
3.It seems Project logic is not the critiria
4. It seemsTask ID is not the critiria

How can i contol the order of the tasks ?
 
D

Dale Howard [MVP]

shoham --

I believe the default sort order is by task name, in ascending order. This
is lame, because the default sort order needs to be by Start date. Teach
your team members to click the Start column header to set sorting on the
Start date. Hope this helps.
 