I have an administrative project for which I changed the booking type for all
resources to proposed and republished the project.

These tasks still remain on all resources timesheets. Any idea what the
issue is and how I can get them removed?
 
J

Jonathan Sofer

What option did you use to republish the project, there are 4 of them and
they don't all fully publish the information as you would expect?

Did you validate that the new proposed state for your resources has been
pushed out to PWA?

Also, did you try to change the booking types via PWA>Project>Build Team to
see if that worked?

Jonathan
 
J

JodyJ

I originally tried Publish All Info which typically works.

I tried Republish Assignments and that seemed to do the trick.
 