S
Steve
I am in "teach myself Project" mode and have encountered a problem that has
me perplexed.
I created a custom calendar for the project, cleverly called "Proj
Calendar". This calendar defines Mon-Sat as work days. Mon-Fri work 10 hrs,
8-12, 1-5, 7-9. Sat works 8-12 and 1-5. Sunday is off. However, I defined
a second "Work Week" called "Spec Sun". It consists of one Sunday (July 19)
and defines it as 8-12, 1-5 work day.
When I look at the "Change Working Time" dialog box and click on any day, I
get the correct hours.
I assigned this calendar to the project, and also to all four resources that
I defined.
When I add a task, it seems to ignore this calendar. The task I added was
given a Constraint of "Must Start On" and date of Sunday July 19 at 8:00 am.
I left the Calendar set to None. The task duration is 4h.
I assigned one resource - me - to the task. I have the "Proj Calendar"
assigned to my resource record.
When I add the task, the GANTT chart shows it starting 7/19 at 8:00 am (as I
would expect) but not finishing until 7/20 at 12:00 pm. It acts like Sunday
is a non-work day and the task is thus done on Monday morning.
When I change the task to explicitly give it the "Proj Calendar", then it
shows the task ending 7/19 at 12:00 pm as I would expect.
OK - so I could simply assign the calendar to every task, but the Project
Help (and MS' website) explicitly say that a task with a calendar of "None"
uses the project calendar by default. I even display the "Task Calendar"
column and it shows "None".
I don't want to have to manually change every new task to the correct
calendar. Am I missing something? Everything I have read seems to say my
task should have the correct project calendar.
Thanks
me perplexed.
I created a custom calendar for the project, cleverly called "Proj
Calendar". This calendar defines Mon-Sat as work days. Mon-Fri work 10 hrs,
8-12, 1-5, 7-9. Sat works 8-12 and 1-5. Sunday is off. However, I defined
a second "Work Week" called "Spec Sun". It consists of one Sunday (July 19)
and defines it as 8-12, 1-5 work day.
When I look at the "Change Working Time" dialog box and click on any day, I
get the correct hours.
I assigned this calendar to the project, and also to all four resources that
I defined.
When I add a task, it seems to ignore this calendar. The task I added was
given a Constraint of "Must Start On" and date of Sunday July 19 at 8:00 am.
I left the Calendar set to None. The task duration is 4h.
I assigned one resource - me - to the task. I have the "Proj Calendar"
assigned to my resource record.
When I add the task, the GANTT chart shows it starting 7/19 at 8:00 am (as I
would expect) but not finishing until 7/20 at 12:00 pm. It acts like Sunday
is a non-work day and the task is thus done on Monday morning.
When I change the task to explicitly give it the "Proj Calendar", then it
shows the task ending 7/19 at 12:00 pm as I would expect.
OK - so I could simply assign the calendar to every task, but the Project
Help (and MS' website) explicitly say that a task with a calendar of "None"
uses the project calendar by default. I even display the "Task Calendar"
column and it shows "None".
I don't want to have to manually change every new task to the correct
calendar. Am I missing something? Everything I have read seems to say my
task should have the correct project calendar.
Thanks