We use Task updates in project 2007 sp1 environment. (dont use timesheets at
all). In our matrix org structure, the resources submit updates to tasks and
those are accepted by the PM each day. If a PM is on vacation or if he is
slacking, it throws off the allocation view for the Line managers. Is there a
way to create a view or cube that shows the list of tasks that have been
submitted by resources across a timephase.
Project 2003 had a link called Adjust Actuals and it provided this
information. Unfortunately i am unable to find anything similar in MSP07. Any
help is really appreciated.
all). In our matrix org structure, the resources submit updates to tasks and
those are accepted by the PM each day. If a PM is on vacation or if he is
slacking, it throws off the allocation view for the Line managers. Is there a
way to create a view or cube that shows the list of tasks that have been
submitted by resources across a timephase.
Project 2003 had a link called Adjust Actuals and it provided this
information. Unfortunately i am unable to find anything similar in MSP07. Any
help is really appreciated.