"tasks" tab in Project Web Access

B

Benedykt

Hello,

I use MS Project Server 2003. When I assign task to some resource
(user), and then I log in as this user to Project Web Access, and I
go
to the "tasks" tab - I can't see that tasks in tasks list. The list
is
empty. However, I can do (still in Project Web Access) "actions ->
assign me to a new task". And then, when I assign a user to a new
task
in this way, this task is visible in tasks list.

Why can't I normally see user's tasks in "tasks" tab in Project Web
Access?
 
J

JennPenn07

Hi, You did not mention if you published the tasks after assigning the
resource. Tasks will not display in the resources task page in PWA until
they've been published first. IF you've published and they still dont apear,
check that when the resource is logged in and on the Task page, under tasks
displayed "all tasks" is selected. Hope that helps.
 
B

Benedykt

JennPenn07 said:
Hi, You did not mention if you published the tasks after assigning the
resource.

No, I did not - I didn't know I have to. Now, when I publish
assignments, everything works ok.

Thank you!
 