S
steelerfan624
I've got a task that requres a user to use a specific piece of hardware that is only available for a certain amount of time per day (say 4 hours). So, what I've done is created 2 resources.....one for the person, one for the hardware. I've set the availability for the hardware to be 4 hours per day.
If I set my task to be a duration of 20 hours, I would like to see 5 days as the duration. I'm not sure how to tell project that this task needs both resources at the same time. Can anyone suggest a good way to do this?
If I set my task to be a duration of 20 hours, I would like to see 5 days as the duration. I'm not sure how to tell project that this task needs both resources at the same time. Can anyone suggest a good way to do this?