U
Uttkarsh Kalia
Hi All,
I am using EPM 2007 with SQL Server 2005 on small scale deployment.
Problem: Project Manager publishes certain tasks in a plan, task update
notification emails are going to all the members in the team.
I would like to have notifications on task updates to be sent only to the
resource assigned for that particular task.
Example, a task start and end date changed, I want to publish only that
particular task in the plan, and I want a notification to be sent to the
resources assigned for that task only.
Steps performed:
1. Open Project Professional login to the Project Server.
2. Open exiting published project plan and make changes to a task activity.
3. Insert Column Publish and from tasks id 1-3 select NO.
4. Task ID 4 select YES and Publish the project plan.
Any suggestions or recommendation will be highly appreciated.
Thanks in Advance!
UK
I am using EPM 2007 with SQL Server 2005 on small scale deployment.
Problem: Project Manager publishes certain tasks in a plan, task update
notification emails are going to all the members in the team.
I would like to have notifications on task updates to be sent only to the
resource assigned for that particular task.
Example, a task start and end date changed, I want to publish only that
particular task in the plan, and I want a notification to be sent to the
resources assigned for that task only.
Steps performed:
1. Open Project Professional login to the Project Server.
2. Open exiting published project plan and make changes to a task activity.
3. Insert Column Publish and from tasks id 1-3 select NO.
4. Task ID 4 select YES and Publish the project plan.
Any suggestions or recommendation will be highly appreciated.
Thanks in Advance!
UK