A
Andy
I have some tasks that I have made a new calendar for so that they can be
completed on a Saturday. When I assigned the calendar to the task, it
removes the task from the critical path. When I filter for the critical path
it shows the summary task of those that are assiged the Saturday work day,
but none of the subtasks. I believe that it is still on the critical path as
the Saturday was required to meet the Monday deadline and there are no other
tasks that finish later that are predecessors for the Monday deadline.
Any advise would be greatly appreciated.
Thanks,
Andy
Thak
completed on a Saturday. When I assigned the calendar to the task, it
removes the task from the critical path. When I filter for the critical path
it shows the summary task of those that are assiged the Saturday work day,
but none of the subtasks. I believe that it is still on the critical path as
the Saturday was required to meet the Monday deadline and there are no other
tasks that finish later that are predecessors for the Monday deadline.
Any advise would be greatly appreciated.
Thanks,
Andy
Thak