sylva
when I schedule tasks the constraint changes to a start no earlier than date
which is ok and what I would expect , however if i then schedule all
incomplete work forward it will not schedule any task with a start no earlier
constraint even though the date is later this does not seem logical and I
can,t seem to find a setting in any of the options to correct this .As many
of the tasks are been moved back it means changing this constraint on them
individually this did not occur in earlier versions and makes the scheduling
very time consuming any advice would be very welcome
does anyone else suffer with this i think i did read that this was a problem
with 2002 and a service pack should cure it but cant find anymore information
about it. where does microsoft now store the pages which use to show all
known clitches in its programs
which is ok and what I would expect , however if i then schedule all
incomplete work forward it will not schedule any task with a start no earlier
constraint even though the date is later this does not seem logical and I
can,t seem to find a setting in any of the options to correct this .As many
of the tasks are been moved back it means changing this constraint on them
individually this did not occur in earlier versions and makes the scheduling
very time consuming any advice would be very welcome
does anyone else suffer with this i think i did read that this was a problem
with 2002 and a service pack should cure it but cant find anymore information
about it. where does microsoft now store the pages which use to show all
known clitches in its programs