M
Mariano Duran
I have a macro in my MSProject that take information from
three different files (Tasks, Roles, Assignments) and
imported the information into MS Project.
The problem is that I can have tasks with 0 effort and 0
duration that are not MIL => when the macro is run that
tasks are converted to MIL without taking into account
the "Milestone" field that say "No".
I can go manually and update that row and set the
field "Milestone" to "No" and everything works as I should
expect.
Is there any workarround to avoid letting MSProject to set
the field Milestone to "No" if the duration is 0 ?
Is there any Visual Basic alternative to change those
tasks not to be a MIL ?
three different files (Tasks, Roles, Assignments) and
imported the information into MS Project.
The problem is that I can have tasks with 0 effort and 0
duration that are not MIL => when the macro is run that
tasks are converted to MIL without taking into account
the "Milestone" field that say "No".
I can go manually and update that row and set the
field "Milestone" to "No" and everything works as I should
expect.
Is there any workarround to avoid letting MSProject to set
the field Milestone to "No" if the duration is 0 ?
Is there any Visual Basic alternative to change those
tasks not to be a MIL ?