E
ehimrod
I am using Microsoft Project Manager 2007, and am wondering if there is a way
that I can set it up so that each task can have multiple "finish" dates
calculated for me. I'm working with shipments that are in my area for
approximately 10 weeks. During that period, I need to do something with them
at week 5 and week 9. Each shipment would be what the program calls a task.
I have tried using Start, Finish (week 5), Start1, and Finish1 (week 9),
with separate durations for each, but the program only recognizes the first
Start and Finish. If the past, I have just used one set of Start and Finish
dates, then calculated out the rest manually, but I'm wondering if there is
an easier way to do this.
that I can set it up so that each task can have multiple "finish" dates
calculated for me. I'm working with shipments that are in my area for
approximately 10 weeks. During that period, I need to do something with them
at week 5 and week 9. Each shipment would be what the program calls a task.
I have tried using Start, Finish (week 5), Start1, and Finish1 (week 9),
with separate durations for each, but the program only recognizes the first
Start and Finish. If the past, I have just used one set of Start and Finish
dates, then calculated out the rest manually, but I'm wondering if there is
an easier way to do this.