M
MalkiaSashko
Hello,
Suppose I have a project that includes the execution of severa
consecutive investment projects. An investment project consists o
several steps: pre-feasibility study, cost-benefit analysis, designin
and construction of a plant. Now imagine a task that must run throughou
the duration of an investment project - say publicity of the investmen
project. It is logical that this task has a start-to-start link with th
pre-feasibility study and a finish-to-finish link with the constructio
of the project. It would also be logical that the duration of this tas
is determined by the durations of all other tasks - if any of them i
delayed, it must be possible that the project publicity task increase
in duration automatically. However, in Project I have to enter a fixe
value for a task. In this case I must manually calculate the duration o
the investment project and enter it as a value for the duration of th
publicity task. However, if during the course of the project there is
delay in any of the task, I have to perform the same calculation agai
and enter the new value for the duration of the publicity task.
Does anybody know a way around this, so that the duration of the las
task depends on the duration of the previous tasks and so that I don'
need to constantly oversee if the values match? Thank you
Suppose I have a project that includes the execution of severa
consecutive investment projects. An investment project consists o
several steps: pre-feasibility study, cost-benefit analysis, designin
and construction of a plant. Now imagine a task that must run throughou
the duration of an investment project - say publicity of the investmen
project. It is logical that this task has a start-to-start link with th
pre-feasibility study and a finish-to-finish link with the constructio
of the project. It would also be logical that the duration of this tas
is determined by the durations of all other tasks - if any of them i
delayed, it must be possible that the project publicity task increase
in duration automatically. However, in Project I have to enter a fixe
value for a task. In this case I must manually calculate the duration o
the investment project and enter it as a value for the duration of th
publicity task. However, if during the course of the project there is
delay in any of the task, I have to perform the same calculation agai
and enter the new value for the duration of the publicity task.
Does anybody know a way around this, so that the duration of the las
task depends on the duration of the previous tasks and so that I don'
need to constantly oversee if the values match? Thank you